Workshop foundation poured through a New Brunswick January
155 m³ of 25 MPa concrete in seven-foot walls for a 6,500 sq ft workshop, formed and placed in winter conditions and finished in January 2025.


A January pour on an open site with snow on the ground from the first footing to the last wall.
- 01 — What was asked for
A 6,500 square foot workshop needed its structural concrete: footings and seven-foot walls, on an exposed site, in the middle of winter.
- 02 — What we did
The crew formed and placed 155 m³ of 25 MPa concrete in seven-foot walls with snow on the ground throughout. The forming ran off a telehandler working from the plowed perimeter.
- 155 m³ placed in winter conditions
- Seven-foot walls formed on an exposed site
- Work kept moving through the January weather
- 03 — How it finished
Structural concrete complete January 2025.
Other concrete jobs

Shop foundation and footings with a 35 m³ single pour
Footings and five-foot foundation walls for a 7,200 sq ft ServiceMaster shop — 48 m³ total with a 35 m³ single pour, done by a five-person crew.
Read the case study
Footings and foundation walls for an 18-unit block
Approximately 230 m³ of 25 MPa concrete placed in nine-foot walls on strip footings for an 18-unit residential development in Saint John, run by a four-person crew.
Read the case study
Twelve-foot walls for employee housing at St. Andrews
Concrete-only package for an employee apartment building at St. Andrews — 120 m³ placed in twelve-foot walls by a six-person crew, complete in September 2025.