Barn, dairy and equipment shop floors across New Brunswick.
Built for how they actually get used: clear-span floors with drainage falls that work, finishes that survive wash-down, and thickness and reinforcement sized for the equipment that will sit on them.
Why an agricultural floor is not just a slab
A dairy floor has to shed water to a trench without ponding, take a pressure wash daily, and stay grippy under a wet hoof. A potato storage floor has to carry loaded equipment on a surface that will not dust. An equipment shop floor has to take point loads from a jack stand without cracking.
These are different problems from a warehouse floor, and pricing them like a warehouse floor is how they go wrong.
- Drainage falls set and checked before the pour, not chased with a grinder afterwards
- Finish selected for wash-down and traction, not for flatness numbers
- Thickness and reinforcement sized to the equipment that will actually load it
- Trench and channel detail poured in, not cut in later
What we can put on the ground
The numbers we work to on a job like this one.
Projects in this scope
Square footage, spec and schedule on every one. We keep the record on every job so we can measure what we did and improve on it next time out.

Footings, walls and slab for a spec house in the woods
Footings, foundation walls and slab for a spec house at Durham Bridge — 40 m³ placed by a five-person crew.
Read the case study
Twelve-foot walls for employee housing at St. Andrews
Concrete-only package for an employee apartment building at St. Andrews — 120 m³ placed in twelve-foot walls by a six-person crew, complete in September 2025.
Read the case study
Workshop foundation poured through a New Brunswick January
155 m³ of 25 MPa concrete in seven-foot walls for a 6,500 sq ft workshop, formed and placed in winter conditions and finished in January 2025.
Read the case studyLet’s talk about your barn or shop floor and we’ll come back with a price